Capacity math on your panel

A circuit delivers at most volts × amps: a 120 V / 15 A circuit tops out around 1,440 W usable (80% continuous rule); a 240 V / 30 A circuit around 5,760 W. Breakers trip on sustained loads above ~80% of rating — mining runs 24/7, so the continuous rule always applies.

CircuitUsable continuous (≈80%)Hosts
120 V / 15 A≈1,440 Wone mid GPU + headroom
120 V / 20 A≈1,920 Wone big GPU rig, barely
240 V / 30 A≈5,760 Wseveral ASICs / a GPU wall
Service entry 100 A @ 240 V≈19 kW whole-houseshared with everything else in your life

Also check: service entrance capacity (the whole house budget), breaker availability, wire gauge and outlet condition, and whether the circuit is shared with anything that cycles (fridge, AC).

02

The review process

  • List every load that will run simultaneously — miners, cooling, networking, plus the household baseline.
  • Ask the utility for a service-capacity check if you plan to add more than ~20% of the panel rating.
  • Licensed electrician for any new circuit or 240 V work — permits and insurance exist for a reason.
  • Record the result: a one-page 'site capacity sheet' (circuits, amps, allocated watts) you update per expansion.
03

See it live on pow.family

Our project quick-starts note per-coin power envelopes from real rigs — multiply against your capacity sheet before purchase, not after.

Sources

Related
More explainers
updated 2026-10-19ASIC vs GPU vs CPU: three ways to hashupdated 2026-10-19Bitcoin block rewards: subsidy, fees, and the coinbase transactionupdated 2026-10-16Emission schedules: why coins halve, decay, or never stopupdated 2026-10-16Merged mining (AuxPoW): one electric bill, two coinsupdated 2026-10-19The mining budget checklist: the true cost of a rigupdated 2026-10-19Electricity costs: the kWh math that dominates miningupdated 2026-10-19The mining glossary: every dashboard word, definedupdated 2026-10-16Pool mining vs solo mining: the variance tradeupdated 2026-10-16What is mining? The hash lottery and the block rewardupdated 2026-10-19Algorithm compatibility: hardware must match the puzzleupdated 2026-10-19Bitcoin difficulty: the 2,016-block thermostatupdated 2026-10-19Home installation: prep and the safety checklistupdated 2026-10-16How pools work: shares, the payroll ledgerupdated 2026-10-16Mining algorithms: SHA-256, Scrypt, RandomX — and why hardware differsupdated 2026-10-19Reading electricity tariffs: energy, demand, and fixed feesupdated 2026-10-16Tail emission and dilution: caps vs forever-moneyupdated 2026-10-19Airflow and temperature: the intake-exhaust loopupdated 2026-10-16Auditing supply claims: three formulasupdated 2026-10-19Halving planning: model subsidy cuts without the folkloreupdated 2026-10-16Mining difficulty: the network's thermostatupdated 2026-10-16Effort and luck: reading a pool roundupdated 2026-10-19Reading miner specifications (and their units)updated 2026-10-19Stratum: how your miner talks to a poolupdated 2026-10-19Time-of-use rates: scheduling mining around the clockupdated 2026-10-19Miner vs node: who actually enforces the rulesupdated 2026-10-19Your first miner: the go/no-go checklistupdated 2026-10-19Demand charges: you're billed on your peak, not just your kWhupdated 2026-10-19Monitoring baselines and safe restartsupdated 2026-10-16PPS, PROP, PPLNS: how pools payupdated 2026-10-16Hashrate: what those TH/s numbers actually meanupdated 2026-10-19Confirmations: why 'confirmed' is a probability, not a switchupdated 2026-10-19Mine or buy? The honest comparisonupdated 2026-10-19Miner efficiency: the J/TH that decides who survivesupdated 2026-10-19Securing the operation: management access and payout custodyupdated 2026-10-16Stale shares and latency: why ping barely mattersupdated 2026-10-19Buying used miners: inspection and seller checksupdated 2026-10-19Payout address safety: the one typo that costs everythingupdated 2026-10-19Measure your miner's real power drawupdated 2026-10-19Reading profit estimates, sensitivity, and payback honestlyupdated 2026-10-19Reconciling pool payouts: expected vs actually paidupdated 2026-10-19Network difficulty vs share difficultyupdated 2026-10-19Rejected shares: the troubleshooting ladderupdated 2026-10-16Choosing a pool: the actual checklistupdated 2026-10-19Cooling and heat: every watt becomes heatupdated 2026-10-19Uptime, availability, and reconciling the energy model
Site electrical review: before you add load · pow.family